Wednesday, March 11, 2020

Public meeting March 18 to answer questions and hear input on Veterans Memorial Bridge project

The Veterans Memorial Bridge

The public is invited to ask questions and offer input on the Veterans Memorial Bridge Rehabilitation Project at a meeting on March 18, 3-8 p.m. at the District Administration Center, 200 North 5th Street.

The bridge project, which was to have begun this year, has been given a new start date of 2023. The meeting is intended to be a fairly informal, "drop-in" affair with borough officials and PennDOT representatives.

Columbia Spy posted the following information about the project on March 19, 2018, some of which may have changed in the interim:

The $54-60 million reconstruction and rehabilitation project will include a refurbished deck with an 8-foot-wide walking lane, two 8-foot bicycle lanes (on the north and south sides), and two 9-foot traffic lanes in the center. The narrower traffic lanes will be a deterrent for speeders, Lutz said. All lanes will be separated with white traffic lines. 

Additional construction will bring the bridge into compliance. Of concern is a bridge arch that has "frozen" into place above its bearing and caused a significant crack. (All bridge arches rest on bearings, allowing expansion and contraction.) Despite the cracking, the bridge is rated "fair" and is considered safe. The underside of the bridge will be completed before deck work begins, Lutz said. Lights might also be added to the underside to help keep mayflies off the road surface and to beautify the bridge.

Two options are being considered for construction: closing off one lane of the bridge and having traffic flow in one direction in the remaining lane; or shutting down the bridge entirely, allowing the project to be completed more quickly (in about a year), since workers would not have to interact with traffic. Lutz said the second option is unfavorable because a traffic accident on Route 30 could shut down the Wrights Ferry (Route 30) Bridge also, preventing all traffic from crossing the river. He added, however, that the four lanes of the Wrights Ferry Bridge could quickly be converted to two in such a case, using existing median barriers as "gates."

A portion of Rotary Park will be used to stage construction equipment and materials, and the former Columbia #1 Fire Company building along Front Street could serve as offices, Lutz said. RK&K Engineering, PennDOT, and the Lancaster County Planning Commission have already met to discuss the project. Preliminary engineering design work is scheduled for the next year and a half.


LINK


Sunday, March 8, 2020

Art Auction at Columbia Library - Sunday, May 17


Columbia boys basketball season ends with first round state playoff loss

PHILADELPHIA — Up by five points at the end of the first quarter, Columbia committed six turnovers in a second quarter where opponent School of the Future went on a 17-0 run. Future kept its foot on the gas in the third quarter en route to an eventual 71-46 win Saturday afternoon in a PIAA Class 3A boys basketball first round playoff matchup inside South Philadelphia High School.

MORE:

https://lancasteronline.com/sports/columbia-boys-basketball-season-ends-with-first-round-state-playoff/article_80e597f2-60bd-11ea-8e57-f77c1f46adca.html?utm_medium 

Attendants may direct spectator traffic during Columbia district basketball games

Lauren VonStetten, chair of the extracurricular committee, reported parental concerns over "nonstop" foot traffic at the Crimson Tide's home basketball games. Because both bleachers in the high school gymnasium were built in close proximity to the basketball court, spectators regularly wander onto the court, causing either a referee stoppage or other safety issues. To solve this problem, the district will consider using baseline attendants to monitor and police spectators who enter or exit the stands during play.

MORE:

https://lancasteronline.com/news/regional/attendants-may-direct-spectator-traffic-during-columbia-district-basketball-games/article_562ac4a8-6174-11ea-a67d-6f48788a2b5f.html?utm_medium 

New geological guide to Northwest river trail offers hikers a fun, rocky tour

The 14-mile Northwest Lancaster County River Trail along the Susquehanna River has been tremendously popular since it opened in 2014. And for good reason. It's a beautiful path along the river with such varied attractions as Chickies Rock, the White Cliffs of Conoy, remnants of great iron furnaces, canal locks, an eagle nest and the river towns of Columbia and Marietta.

Now, trail users — 120,000 last year — can have a fuller experience with the publication this week of "Geologic Guide to the Northwest Lancaster County River Trail" by Jeri Jones, a York County geologist who loves to share his passion with the public.

MORE:

https://lancasteronline.com/sports/outdoors/new-geological-guide-to-northwest-river-trail-offers-hikers-a/article_919f8418-5f23-11ea-9455-d76be025eb58.html?utm_medium 

Columbia Borough Meetings - Week of March 9, 2020


A dissenting view - Columbia Market House Project: Next financial boondoggle or economic engine?


Columbia Spy previously published this article on December 9, 2019, before the Market House renovation began. It is published here again, because it sheds light on some the recent issues with the project. The author is a taxpaying Columbia Borough resident, whose name is being withheld by request.


The question at hand is whether a 2.0-2.5 million dollar investment in the oldest market house in Lancaster County, with its original detail still intact from the day it was built in 1869, will bring about the economic outcome the current borough council envisions. Through a partnership with a local charity, they propose to create a restaurant, new bathrooms, and 20 market stands along with all new mechanical systems including a massive heating and air conditioning system. In the end, will this project simply be another huge expense of borrowed taxpayer money that will ultimately fail to generate enough money to pay for the operation and maintenance of the facility long term, let alone ever provide enough cashflow to pay back any of the millions in borrowed money. There are arguments on both sides of this question which we will attempt to provide the facts here for readers to make their own judgement.

Background:

First, it is important to understand how we got to the point of being ready to pull the trigger on spending all this money on the market house. In 2016 Columbia engaged a financial services company to raise 10 million dollars in long term bonds to be invested in a variety of projects and paid back over the next 20 years. One of the projects identified for some of this money was the Market House. The Borough solicited proposals in mid-2018 from parties outside the Borough, interested in reopening and operating the market house. The Borough received a total of two proposals and chose to move forward with the one from Catholic Health Initiative (CHI).

CHI Vision and agreement:

CHI proposed to manage the Market House and reopen it with a mix of market stands and a restaurant. CHI and the Borough entered into an agreement where CHI would manage the operations of the Market House for 5 years and contribute up to a maximum of $60,000.00 per year for the 5 years. [Editor's note: The amount is $65,000, according to the Professional Services Agreement between the Borough of Columbia and CHI-SJCH.]  The $60,000.00 would cover electric, gas, janitorial services, and other operating expenses including hiring of an event coordinator. If the operational expenses exceed the $60,000.00 contribution from CHI, the Borough is responsible to cover anything over the $60,000.00. CHÍ also pledged to provide a one time contribution of $100,000.00 towards new market stands, tables and chairs, and other fixtures for the restaurant. The Borough would pay for water, sewer, trash, snow removal, general maintenance of systems, and for all the construction activities including HVAC, electrical, plumbing, fire protection, exterior restoration, general construction and project management. CHI was given the authority in the agreement to manage the entire construction process.

Even though there is an advisory committee with representatives from the Borough (don't know who they are and not aware of any advertisement to fill these positions?) that is to meet quarterly and provide input to the operation of the market house, CHI has ultimate decision making power. Interesting that the taxpayers don't ultimately have any say in the improvements to a building they own, and are to invest 2 million plus in, and pay for over the next 20 years!

In the current management agreement there is no discussion or fee schedule for rentals other than to say the rates will be based on comparable rental rates in the area and nothing about any rental income from the restaurant other than CHI will work with the restaurant operator to come up with a business plan in the first year of operation. Who enters into a contract with someone without some basic projections for revenue and expenses before considering signing a contract, let alone spending millions of dollars? This is ok, if it is between two private parties, but this is taxpayer money being spent on a taxpayer owned property! Time to wake up taxpayers!

Current Status as of 12/4/19

The Borough has received bids for the project from 5 separate trades including General Contractor, Electrical, Plumbing, Fire, Mechanical which including all alternates add up to $xx for the lowest total bid. If you drop the alternates, which you should, the bid comes down to $xx. On two of the trades there was only one bidder which means there was no competitive process so we really don't know if we are getting the best value for our money. Seems like it might not be a bad idea to at least consider rebidding those trades?

Borough Council discussed the bids with the project architect at the Council work session on 12/3 and appears ready to approve all the bids, even though they would not have to, at the next Council meeting on 12/10. At this work session no one on Council asked any questions about the pricing or brought up possibility of make some changes or rethinking some of the systems and design to minimize the impact on the historic building and save some money. The fact that no elected person even expressed concern about the amount of money shows that this project must be put on hold until the new council people can review the project and decide how they want to move forward. The new council may want to review the agreement between the Borough and CHI and update it to include clearly defined financial goals and allow for greater involvement of the borough and its taxpayers in decision making.

Funding:

So how are we paying for all of these improvements?

The Borough already has a commitment of $200,000.00 for Lancaster Counties Block Grant Program. The balance of the funds would come from the Borough matching a grant from the State. If the project is 2.2 million then the Borough would put in 1.0 million which would come from the bond issue as discussed above. This is borrowed money, not money we have in the bank! The Borough currently owes about $400,000.00 annually on this bond issue and the payments will continue to rise until paid back in 2027.

Financial considerations:

What happens once CHI no longer contributes the $60,000.00 per year and the Borough is responsible for the entire cost of operating and maintaining the market? At a minimum would the Borough be prepared today to commit $60,000.00 a year minimum to the market as a line item in the budget? If we are not prepared now to make this contribution, what would change in a few years once CHI is no longer involved, that we could make this commitment? The market house has been closed at least two times in the last 20 years because the Borough said it could not generate enough revenue to offset the amount of money the Borough was spending to keep it open even though it was bringing in some revenue. This amount was far less than $60,000.00 to keep it open in the past.

Again, there has been no discussion by our elected officials how this enterprise will ever come close to break even without a substantial annual contribution from the taxpayers. We are not saying it is wrong for the taxpayers to support the market house, but it certainly deserves adequate review and consideration along with factual financial projections, not just wishful thinking, as to the taxpayer contribution that will be necessary in the next 5 years, 10 years, to sustain the market as conceived in the plans. This would be a normal step taken by any responsible local government!

If for a moment, we assume the annual operating expenses are near the $60,000.00 figure, you would have to collect at least that amount from rental income from the Market House to cover the expenses that CHI plans to cover with this amount. Keep in mind the Borough is still paying for water, sewer, trash, snow removal, maintenance of systems from the beginning so even if you did collect rents to cover the $60,000.00 the Borough would still have additional expenses on top of that number, so the actual total cost of operation could be higher than the $60,000.00. This begs the question, can we collect enough rental income to cover the costs of operation on an annual basis and if not, how much money is the Borough willing to dedicate out of the budget to keep the Market House open. When you apply some simple math to this question you come up with a resounding NO!

Impact of Proposed Changes on Historic Structure:

The impacts of this project are not just about the positive or negative effect on the budget but more importantly the impact on a one of kind, historically significant structure, in original condition that with the proposed improvements will look more like a gymnasium than a historic market house. With these proposed changes costing millions of dollars, it will still be an old building but the structure will be forever altered and its historic integrity will be gone!

Unfortunately, these changes have been conceived and put into the construction drawings by people with all good intentions, but not the training and experience in working with historic structures like the market house, so they simply design systems that you would find in any other new building where historic considerations are not an issue. Many professionals today say they are involved in historic preservation but few have the actual skills to do it properly.

Examples of proposed changes:

The view of the original wooden ceiling trusses will be blocked by huge 34" ductwork wrapping around 3 sides of the building. These wooden trusses and barrel vaulted ceiling are one of the most significant original features in this structure, and should not be blocked from view with ductwork that looks like an octopus hanging from the ceiling. There are better and more efficient ways to heat and cool this structure.

Holes drilled into the wooden trusses for hanging ductwork, pipes, conduits.

Taking up the original brick floor and replacing most of it with concrete. The decision to remove the brick floor is based making it easier to install some mechanical systems but is not based on maintaining the original features of the building and finding a different way to make the improvements.

These are just a few examples of areas that need to be reviewed and given careful thought before proceeding with improvements as they are very costly and therefore cannot be changed after the fact. Another reason to take a breath and allow the new council to review all documents and plans before signing contracts that they may have to cancel!

Value Engineering:

In most construction projects, there is a process called value engineering, which many times occurs after the project bids come in but before final contracts are signed. It is not uncommon for individual bids, or the collective total of the individual bids, to be higher than expected.

Most clients include everything in the proposed project they would like to have, while realizing the price for everything, may be more than they want to spend and this is where the value engineering process comes in. There is no reason not to engage the new Council and anyone else from the community that may have input on ways to reduce the overall cost of the project and reduce long term operation and maintenance costs. We only get one chance to do this project right! There is no question that this process would produce results.

One area you can definitely save money on is the HVAC system. It will not only alter the historic character of the building; it is not necessary as currently designed to make the operation successful and in fact will be a major financial drain on ongoing operating costs. See comment below on Lancaster Central Market.

Food for thought

Was the Council's decision to move forward on this project based on sound financial analysis or was it driven by inflated egos that were eager to spend the millions of dollars raised through the bond funds on projects from A-Z whether they made sense or not? By signing the contract with CHI the Council took the easy road of passing all responsibility to an organization outside of the Borough so they could grab headlines and say big things were happening in Columbia. Not that this is a bad thing on the surface but at the same time they short changed the taxpayers on due diligence and proper input into the design process.

There is a reason history repeats itself. History keeps repeating because instead of learning from the past we keep repeating the same mistakes over and over. When the Market House was reopened 20 year ago, instead of following the plan that had been developed with input from people who were running successful markets, we continued to go further and further away from what all parties had advised until it was closed again. Now, we somehow think this time it will be different because we are going to spend even more money, so it will have to be successful. The experiment we are about to engage in with the market house has been done before in other communities and did not prosper.

What happens if within a year or two the restaurant operator decides to leave because they are not making enough money to pay rent and earn a living? We now have a market house with a commercial kitchen and all the other million-dollar improvements that is empty and no income from operations. True, you could find another person to run the restaurant but if the first operation did not do well what are the odds the second, third, fourth will do any better?

It was stated by a representative from CHl at the December 3 council work session that they are now planning to start with 4 market stands and let the rest of the stands grow organically including having the vendors pay for their own stand. This will never work. The market stands will never be able to pay enough rent to even remotely cover the cost of keeping the doors open!

CHI is a charity. It is great they are willing to partner with the borough to try and bring life to the market house but we have to be careful as CHI is a charity and so they are in the business of donating money and providing services that assist underprivileged people and communities like Columbia. The Borough, on the other hand, is not a charity, it is a municipality that has an obligation to carefully manage the money they receive from taxpayers.

Will the newly elected borough council people, who promised during the campaign to rein in all the debt driven spending that has been going on over the last few years, take a stand on the market house project, and as a public official uphold the top priority of fiscal responsibility?

Lancaster central market considered installing A/C and did not do it-

Why did they not do it?

Arguments for why not to take a pause and carefully consider the potential outcome of spending 2.0 million on the Market? If we delay awarding the bids by a couple of weeks or even a month it will delay the opening of the restaurant. -Since it is only a couple of weeks until the Christmas and New Year's Holiday no major construction would occur anyway so this argument is no good.

Is Columbia accountable to the operator of the restaurant or the taxpayer?

Why is the restaurant operator the top priority here?

Making sure that taxpayer money is spent wisely on something that can benefit the community long term is way more important than a tenant that according to the agreement, has no commitment to invest any money in the project. You would think Mr. Diller would have no problem with the newly elected Council taking a look at the plans and CHI agreement and making sure they are in agreement with everything before proceeding since they will be the ones to sign the checks to pay for it and they will be the ones who will have to answer to the taxpayers who they told that they would get the crazy spending spree under control.

It was reported in the LNP news on December 1st that the market house is part of a project that is adding downtown parking at a cost of at least 3.5 million. Interesting that you have to read the paper to find out that the town you live in plans to spend 3.5 million? Also interesting that we just started a parking study on December 6th but somehow without even getting started with that study we are already planning to spend more millions? Anybody see a problem here with how these projects are moving forward?

Mr. Diller commented in the article that he was closing his current location in Lancaster by the end of the year, and would be preparing meals for office workers in the meantime until the Columbia Market House renovations are finished later this year. Doesn't sound like Mr. Diller would object if the new council wanted to take a look at the details of the project.